变电站电缆沟防火墙电缆预留通道的改进论文_王凯

甘肃送变电工程公司 甘肃省 730070

摘要:改进后的变电站电缆预留通道,是在电缆沟防火墙上安装复合电缆槽盒,以取代现在通用的白色PVC管。具有制作简单、成本低廉、实用性强,有效期长,便于变电站扩建、改建工程电缆敷设、检修及电缆更换等特点。大大地节约施工时间、施工费用,同时降低了在运行变电站施工的安全风险。保障了电缆安全可靠运行,提高了变电站运行管理水平。

关键词:变电站 电缆沟 防火墙 电缆预留通道

Abstract:the improved substations reserved channel,in cable trench firewall installed composite cable tray,white PVC pipe to replace the general now. Has a simple,low cost,strong practicability,validity period is long,is advantageous for the substation expansion,rebuilding engineering cable laying,maintenance and cable replacement,etc. Is greatly cut down the cost of construction time,construction,and reduce the running of transformer substation construction safety risk. To ensure safe and reliable operation of the cable,raise the level of the substation running management.

Keywords:substation in cable trench firewall cable reserved channel

1目前电缆预留通道的现状与分析:

近年来,变电站改建(智能化、数字化和综自改造)、扩建工程多。在进行电缆敷设过程中,电缆穿过电缆沟防火墙上电缆预留通道(白色PVC管)时,由于白色PVC管的数量及管径与敷设的电缆外径、数量不符,严重影响电缆敷设后的工艺美观。特别是各小室电缆沟入口,施工时只能拆移防火墙,电缆敷设完成后重新进行开孔封堵。不仅增加施工任务、施工时间及施工费用,最主要还存在较大的施工安全风险等问题。为满足改、扩建变电站工程电缆敷设及保障运行电缆安全可靠运行,经过多次研究,设计出电缆沟防火墙上的电缆预留通道的改进方案。

2电缆预留通道改进方法及应用

变电站电缆沟防火墙电缆预留通道改进的指导思想为:实现外观美化与内在实用性最佳结合。

2.1、复合电缆槽盒尺寸:长x宽x高(400mmx200mmx100mm);封板尺寸:长x宽(200mmx100mm),通道大,便于电缆敷设排列。

(如图1)

2.2、在电缆防火墙上安装复合电缆槽盒作为电缆预留通道,以此取代现在通用的白色PVC管。电缆槽盒的两端加装活动封板(与复合电缆槽盒是同一材质)。活动封板有两种打开方式:

(1)从电缆槽盒侧面打开(如图2):当电缆槽盒封板上方的空间——垂直高度小于100mm时,封板向上不能取出,只要将封板的活动托架的固定螺丝松开,就可以从侧面取出封板。

结论

改进后的电缆沟防火墙电缆预留通道,外观美化,制作简单、成本低廉、实用性强,便于改、扩建变电站工程电缆敷设。经过在哈达铺变、金塔变实践,达到了很好的预期效果。已经在全公司推广。该工艺改进既降低了施工安全风险,又保障了电缆的安全可靠运行,提高了变电运行管理水平,突出了科技和管理创新,有一定的创造性,具备普遍推广意义。

参考文献:

[1] 国家电网公司输变电工程标准工艺库(2012)

论文作者:王凯

论文发表刊物:《基层建设》2016年7期

论文发表时间:2016/7/9