大跨度重型钢桁架逐单元滑移施工技术论文_林业康

广西建工集团第一建筑工程有限责任公司 广西南宁 530001

摘要:结合工程实际,介绍了大跨度重型钢桁架逐单元滑移施工技术。从施工方案选择、钢桁架的拼装、钢桁架的吊装和滑移、钢桁架的卸载等方面,对单榀钢桁架的安装方法进行了总结,取得了良好的社会效益与经济效益,对同类工程施工具有一定的参考价值。

关键词:大跨度,重型钢桁架,逐单元滑移,高空安装

Construction technology for unit-by-unit sliding of long-span heavy steel truss

Lin Yekang

Guangxi Construction Engineering Group No.1 Construction Engineering Co.,Ltd., Nanning, Guangxi 530001, China

Abstract: This paper introduces the unit-by-unit sliding construction technology of long-span heavy steel truss with engineering practice. From the aspects of construction scheme selection, steel truss assembly, steel truss hoisting and sliding, steel truss unloading, etc., the installation method of single truss was summarized, it has obtained good social and economic benefits, and has a certain reference value for the construction of the same kind of engineering.

Keywords: long-span, heavy steel truss, unit-by-unit sliding, high-altitude installation

1、工程概况

贺州市平桂区扶贫移民综合市场项目主楼工程是贺州市平桂区的一项重点建设项目,建成后将作为东盟博览会贺州分会场进行石材展销,主楼施工内容包括土方、桩基及主体施工,长270米,宽86.5米,单体工程建筑总面积为48454.74㎡,其中三个主展厅钢结构桁架屋盖面积达12600㎡。本工程钢结构工程主要是单片钢方管桁架、次桁架、钢檩条、钢马道及钢支撑组成。展厅屋盖分布在 1-8 轴/B-K轴、17-20 轴/D-H 轴及 29-35 轴/B-K 轴,屋盖长分别为 77.575 米、42.00 米和 77.575米,宽分别为 49.00 米、35.40 米和 49.00 米,屋面标高分别为 21.00m、27.7m 和21.00m,单根钢桁架的重量达38t。本工程钢结构安装难度大,构件运输超宽,部分构件无法运输,必须在施工现场制作。因施工现场作业面不足,钢构件的拼装、组装及吊装将是一个难点和重点(图1)。

4 结语

本文介绍了大跨度重型钢屋桁架逐单元滑移施工的各项技术要点,对钢屋桁架采用工厂预制和现场拼装相结合,缩短施工时间。通过采用逐单元滑移的施工方式,避免了使用大型履带吊安装,节约了施工成本,降低了施工风险。运用滑移纠偏措施,确保了钢屋桁架的安装精度。解决了大跨度重型钢屋桁架高空安装难题,为同类结构的施工积累了相应经验。

参考文献:

[1] 高并强.大跨度钢桁架带柱累积滑移施工技术研究[J].山西建筑,2012,38(27):119-121.

[2] 张同波,邹传学,曲成平.青岛流亭机场航站楼大跨度钢结构施工技术[J].施工技术,2004,33(11):19-22.

[3] 邹科华.大跨度弧形箱梁高空累积滑移施工技术[J].建筑施工,2017,320(39):1759-1761.

论文作者:林业康

论文发表刊物:《防护工程》2018年第29期

论文发表时间:2019/1/2

标签:;  ;  ;  ;  ;  ;  ;  ;  

大跨度重型钢桁架逐单元滑移施工技术论文_林业康
下载Doc文档

猜你喜欢